Project Timeline

Updates Archive


Over the last 12 months, significant progress has occurred with the stained-glass window project and is moving forward:


To Date Recap of Project

  • A plan that included cost estimates was developed and approved by the Consistory
  • A grant application was submitted on June 1st to the NY Landmarks Conservancy
  • A physical site visit was performed on July 31st by a Sacred Sites committee member
  • FRCB received notification on October 21st that it was awarded a $15,000 grant
  • On December 16th, FRCB received the check for the $15,000 grant from the NY Landmarks Conservancy – Sacred Sites Program
  • Vestibule windows returned from being studio restored and were reinstalled on November 14th
  • Bell tower rectangular windows were removed on November 30th for studio restoration

Tentative Schedule Moving Forward

  • Depending on weather, sometime in April the (3) sanctuary Rose windows will be removed for studio restoration
  • Soon thereafter, May or June work will begin on the (12) sanctuary arched windows. The old plexi-glass protective covers will be removed, the exterior frames will be cleaned, scraped, primed, and painted with new exterior trim paint. Finally, new clear vented float glass will be installed.
  • Mid-summer, the Rose windows and bell tower windows will be reinstalled, and new clear vented float glass installed.
  • Late summer, final touches to finish Phase 1 of the Restoration Project.

Future Fundraising Ideas

  • A grant application will be submitted to the Community Foundation of the Greater Capital Region.
  • A wall plaque will be created listing donor names making contributions in memory of loved ones.
  • Do you have additional suggestions?? Maybe a rummage sale, outdoor concerts, more church dinners?? If you have an idea, share it with a consistory member!

To Conclude


The grant received from the NY Landmarks Conservancy through its Sacred Sites Program further adds validity to FRCB’s belief in the importance of maintaining and restoring our sacred site to continue its rich community history dating back to 1763.


Thanks to all for your support of this project! The finished look should be stunning! Check back for updates!!

April 8, 2024 - The window restoration project has begun. The first Rose window has been removed to be taken to the studio for full restoration. The window was removed in sections, leaving the wood frame that will be refurbished in placed. In the interim, the window opening has been covered over with plywood. Work is scheduled to continue the week of April 15th.


April 23, 2024 - All three Rose windows have now been removed and are now at the studio being cleaned and the lead work refurbished. The wood frames have been repaired as needed, primed, painted and readied for the return of the stain glass sections once completed. In the interim, there will be several weeks where nothing will get done until the Rose window sections get refurbished and the weather consistently stays warmer. More to come!


July 3, 2024 - The stained-glass window restoration project is progressing apace! As of June 25th, two of the three restored Rose windows were reinstalled, and restoration of the Gothic arch sanctuary windows has begun. It is unfortunate that the high placement of the Rose windows in the sanctuary limits a real appreciation of the craftsmanship that went into their restoration. Attached are a before and an after picture of sections of a Rose window that show the restored lead work and the benefits of the investment. Please keep in mind as you follow the progression of the project that the remaining windows will gradually go from appearing unfinished to completed. Updates will be provided in July and August as the project continues.


July 31, 2024The stained-glass window restoration is moving right along. As of July 28th, all three Rose windows have been restored and reinstalled with new, vented glass coverings. The restoration of the Gothic arch sanctuary windows is well underway. The major remaining piece to complete the restoration of the Gothic arch windows is installation of new glass coverings for the ventilators. Phase 1 of the project also included the restoration of the four vestibule windows, which is completed, and restoration of the bell tower windows, which will be done upon completion of the work on the Gothic arch windows. With much of Phase 1 of the project completed, we invite you to stop by and see the newly restored look of the windows! The full impact of the restoration is best appreciated from the interior of the sanctuary. Join us for a Sunday morning service to witness the enhanced beauty of the sanctuary as sunlight streams through the windows as we hear God’s word proclaimed.


EXCITING NEWS - Phase 1 of the stained-glass window restoration project is complete! The project included the three Rose windows, four sanctuary front entrance vestibule windows, and two rectangular bell tower windows being studio restored and reinstalled with new vented glass coverings; installation of new glass coverings and ventilators for the (12) Gothic arch sanctuary windows; and new glass coverings for the four circular bell tower windows. Every sanctuary window frame was scraped, and framework touched up with epoxy where necessary, as well as all windows being cleaned, then primed and painted with BEHR Ultra Semi-Gloss Black Limousine Leather.


Please stop by and attend a Sunday service to appreciate anew the beauty of the stained-glass windows as well as the interior of the sanctuary, or stop by to see the exterior look of the windows.